Restrictions on the operation of Oracle databases and some applications and on the update of network elements:
- Tuesday, 18.8. from 9:00 to approximately 11:00, restrictions on the operation of test and development databases
- Friday, 21.8. from 13:30 to 14:00, update of network elements – service availability outages
- Friday, 21.8. from 14:00 to approximately 16:00, restrictions on the operation of production databases
Friday’s shutdown of the production environment is in accordance with the Schedule of Planned Outages for 2026.
Restrictions on database operation will be necessary due to adjustments to the database configuration, which requires the databases to be turned off.
Friday’s update of network elements will cause temporary outages in the availability of all VIC CTU services.
During the database reconfiguration, there will be database availability outages on individual nodes in the database cluster (RAC). Database operation will be maintained. This means that established connections to the database will be interrupted, but it will be possible to establish new ones immediately. Users may experience a connection outage and will have to log in again. We recommend not performing important operations during this time.
The test applications SFIS and iKOS (18.8.) and the production applications iKOS and SFIS (21.8.) will be out of service at the specified times.
Both outages are planned for approximately 2-2,5 hours, but may be extended in case of problems.
The network management department provides the update of network elements. The Oracle database reconfiguration is provided by the server management department.